Construction of formed natural rock fishway ladders, cut/formed soil/rock resting pools and improved shape waterways. (Forsayth)
Client: Etheridge Shire Council
Scope of work
- Excavate locally sourced rock according to excavation sites
- Discussions with project manager and deliver stockpiles close to fish ladders
- Excavate footings. If natural rock on surface, remove loose material and use mortar to bond.
- Mechanically place/physically place rock (size specified in plans) ensuring parts are unmoveable under foot traffic and flowing water.
- Point up
Resting ponds:
- Excavate locally sourced rock and stockpile at resting pools @ approx. 75m intervals.
- Excavate 11 resting ponds according to size specified in plans. Place rock and fix.